Construction
of highway bridges was the principal task in this project. The North
Contract consisted of a 2.7 km long dual 3-lane viaduct. The application of
the precast segmental method proved to be efficient and effective.
In the South Contract the Yau Ma Tei interchange, which is one of the most
complicated grade-separated interchange in Hong Kong, was successfully
constructed by means of conventional in situ method.
Pier
and Abutment
The
expressway decks are supported by a series of T-shape concrete columns
sitting on the pile caps supported on bored piles or barrettes. Some
columns are offset from the positions directly below the deck box spine, in
areas where access ramps are located or where the LAR tracks emerge from
beneath the deck. Where the offset is small, the deck is supported by
a special column head arrangement offset on a single column. Where the
offset is great, a portal arrangement is used with the deck on a cross beam
supported by two discrete columns straddling the obstruction. In view
of the LAR trains run near the columns, the columns are protected by
reinforced concrete deflectors to minimize the impact in case of any derailment.
The piers and
abutment were construction in situ using grade 40/20
concrete. To commence the construction of a pier, a scaffold-working
platform was erected prior to the reinforcement installation. The platform
facilitated the installation work and helped to maintain the rigidity of the
reinforcement. Drainage down pipes, services ducts and box-outs were
installed and reserved where required. The formwork was pre-assembled
into several panels before erecting it in position. The verticality was
checked regularly during the erection. Concrete was placed in layers
by a crane and skip with assistance of chutes to control the free fall height of
the concrete. Compaction was maintained throughout the
concreting work. Sufficient time was allowed for curing before
removing the formwork. Bearing plinths were cast on top of the column
heads to support the bearings. They were cast after the column heads
and were finished to ensure that accurate set-out could be achieved.
In the construction of an abutment, the outside formwork of the abutment
wall was erected prior reinforcement installation. Remaining formwork was
erected after reinforcement had been installed. The construction sequences
are similar to the construction of piers.
Bridge
Deck
Construction of
decks started after the piers were completed. Precast segmental
method was utilized for the construction of the elevated viaduct. Other
bridge structures were constructed in situ using standard falsework and
formwork. Most of the decks were of pre-stressed concrete single or
multi-cell box type. |