The
North Contract consists of a 2.7km long continuous dual 3-lane viaduct
carrying the expressway mainline. The viaduct was designed and
constructed using the precast segmental balanced cantilever method.
The deck was formed from precast segments which were manufactured at the
casting yard and joined together at their final positions.
Construction of the deck started from the top of each pier, with precast
segments added progressively, working away from the pier in a symmetrical
manner in order to maintain balance. This enabled deck erection
to proceed simultaneously on several piers, resulting in a very fast rate
of construction.
The viaduct
was designed to give a high degree of standardization in the construction.
It is divided typically into 236.6m long elements, continuous over six
spans between movement joints. These elements repeat themselves to
form the entire expressway viaduct. The typical internal span
lengths are 42.3m and end spans vary between 30.4m and 37.0m. The
internal span was maintained constant as far as possible while by
adjusting the end span to accommodate obstructions.
Construction
Method Selection
The design
process of the viaduct considered cost, construction time and availability
of resources. A number of structural options including conventional in
situ construction, precast beams or precast segmental construction were
considered preliminary. Precast segmental construction was finally
chosen for the following reasons (Ng, Morris, Wong & Tornet, 1996):
- Precast
segmental construction is largely independent of the ground condition.
It offered the advantage of in situ construction which was relevant
as the extent of the
reclamation at the commencement of the expressway
was uncertain.
- Precast
segments offered an economical form of construction for the 91,750m2 deck area and a 7.3km total box length (including ramps)
comprising 2,258 segments to be constructed.
- The
simple alignment of the expressway allowed a high degree of
standardization and repetition.
- Construction
rate is quicker than in situ or precast beams construction.
- Precast
segments in box girder forms are more aesthetically pleasing than precast beam alternatives.
- Precast
segmental construction is less labour intensive than in situ or
precast beam construction, particularly considering the heavy Airport
Core Programme
civil activities that would be carried out concurrently.
- The
successful completion of the Kwun Tong Bypass in 1989 established the
use of the method in Hong Kong.
Furthermore,
a comparison of the effects of in situ construction and precast
construction on the prestressing force was estimated.
Savings
by using precast construction:
Loss
by using precast construction:
-
Increased friction.
-
Possible misalignment of ducts at the segment
joints.
-
Extra prestress requirement.
-
For segmental construction, in
longitudinal design under serviceability loading, no tension is allowed
across a joint, while compression is required across the in situ stitch at
mid-span under all load cases.
There was a
net increase of 17% in prestress for the segmental deck in the estimate.
This extra cost was compensated by the savings in longitudinal
reinforcement and, more importantly, the savings in reduced casting and
construction cost due to the repetitive nature of factory pre-casting and
deck erection.
Erection
Segments
for the main carriageway were erected using a 90 tonne portal gantry crane
which ran on rail tracks laid along the route of the viaduct. The
portal crane had sufficient span over the twin boxes of the mainline,
which allowed erection of two S7.2 segments side by side. The
smaller slip road deck segments were erected using crawler cranes.
The typical erection rate was one carriageway span per week. Segment
erection commenced in June 1994 and was completed by October 1995, in 17
months.
The segments
were transport to the erection area by delivery trailer. A lifting
spreader beam controlled by the gantry or crane was used to lift the
segment to its final position. The spreader beam was not released until
the temporary pre-stressing bars were fixed. The bars were located at
the top slab between webs, tips of the wing and bottom slab. For
pier segment, the spreader beam was released after the installation of the
four vertical pre-stressing bars through the segment and coupled to the
anchors on the column head.
During the
erection of a segment onto a cantilever, epoxy was applied to the joint
faces to lubricate the surfaces during segment positioning and to seal the
joint against water ingress and transfer shear forces after the epoxy had
hardened. The epoxy also sealed the joint to prevent grout loss
during the grouting of the internal post-tensioned tendons.
After
positioning the segments, and before the epoxy hardened, the joint was put
into compression by the use of temporary pre-stressing bars. These
bars were also used to support the cantilevered segments until the
permanent pre-stressing cantilever tendons were stressed.
Adjacent cantilevers were then joined together by in situ concrete stitches
to form typical six span units. The permanent pre-stressing tendons
were arranged into two groups, those used during the cantilevering process
(cantilever tendons) and those that were installed after casting the
in situ stitch (supplemental tendons). These tendons were anchored in blisters in the internal corners of the box.
During the
construction, vertical and horizontal adjustments of the cantilever
profile if necessary were achieved by using the vertical
jacks located on the temporary supports.
The in situ stitch was cast after
the erection of the last segments of the two cantilevers to be joined.
Two clamping beams were fixed across the top slab of the segments of each
cantilevers to prevent relative displacement of these cantilevers during
casting, concrete setting and post-tensioning works. |